Construction updates, road closures and other important info will be featured below throughout the project.
Construction will soon begin on South Front Street from Grant Avenue to Broad Boulevard.
Preliminary sanitary sewer videoing and survey work took place in Fall 2024. Starting the week of January 13, work will begin on sewer repair. This work will not affect the flow of traffic.
At the end of January, the new traffic pattern will begin. The east side of S. Front Street will close (Sheraton Suites side) and remain closed for several months. All traffic in both directions will be maintained on the west side of S. Front St. There will be no on-street parking. Notices will be distributed when the closure occurs.
Access to all businesses, including driveways and sidewalks will be maintained.
The list of available public parking lots and decks can be found on the project and City websites.
During late spring most of the work will be finished on the east side of S. Front St. Then traffic will flip to the east side while the west side is reconstructed. It is anticipated the project will be completed in Fall 2025.
Construction is anticipated to start in early September.